Case Study

CMS School

6
+ 9

LOCATION

Coimbatore

TOTAL AREA (SQFT)

8000 Sqft

TIME TAKEN TO COMPLETE

4 months

TYPE OF BUILDING/SOLUTION

Steel structural floor addition with composite roof slab

CLIENT BRIEF/THE OBJECTIVE

  • Complete within short period
  • Faster completion of floor
  • Light in weight
  • Composite roof

CHALLENGES (IF ANY)

( Any challenges which was faced in coming Up with the solution.)  Govt. rules and regulations / Old structure they were unaware about strength of building

  

THE CONSTRUCTION PROCESS

(short description on the scale of construction process, materials used, technology etc)

  • HR steel for main frames/Steel tubular frames for walls/ fibre cement board wall cladding /

 

 

THE SOLUTION

( Any challenges which was faced in coming Up with the solution.) - Govt. rules and regulations / Old structure they were unaware about strength of building

 

BENEFITS/ADVANTAGES

After completion : Customer was happy as they got enough space by adding floor.Loaded weight was also less.

 

Sree Ramakrishna hospital

14
+ 5

LOCATION

Coimbatore

TOTAL AREA (SQFT)

70000 Sqft

TIME TAKEN TO COMPLETE

10 months

TYPE OF BUILDING/SOLUTION

Design and build steel structural project / Institutional

CLIENT BRIEF/THE OBJECTIVE

Faster execution / Sustainable construction practices / Looking for a single vendor for taking up full responsibility of design and construction

SOLUTIONS

  • Built up H section for columns & Beams
  • 5 mm thick tubular structure for architectural roof
  • Steel architectural louvers
  • Steel framed façade with ACP skin on the exterior
  • Internal cladding with calcium silicate double layer boards
  • Fire proof using cementacious fire proofing compound
  • One of the first high rise building in Tamilnadu
  • Approvals got after careful structural proof checking by the authorities as it’s a first of its kind building

Sri Lakosha Polymers

DSCN8964
+ 5

LOCATION

Coimbatore

TOTAL AREA (SQFT)

25000 Sqft

TIME TAKEN TO COMPLETE

4 months

TYPE OF BUILDING/SOLUTION

Ware house building with office

CLIENT BRIEF/THE OBJECTIVE

Short description about what the Project objective is or what the client wanted.

CHALLENGES (IF ANY)

Work to be completed within summer school holiday time

 

THE CONSTRUCTION PROCESS

(short description on the scale of construction process, materials used, technology etc)

THE SOLUTION

The actual solution, what Steelion proposed to The client to meet the objective.

KSEB

kseb-shornur
+ 2

LOCATION

Shornur , Kulappulli

TOTAL AREA (SQFT)

15000 Sqft

TIME TAKEN TO COMPLETE

12 months

TYPE OF BUILDING/SOLUTION

Design build steel structural project / Multi storied building – public sector

CLIENT BRIEF/THE OBJECTIVE

Wanted to promote sustainable & Innovative construction practice

CHALLENGES (IF ANY)

Work to be completed within summer school holiday time

 

THE CONSTRUCTION PROCESS

  • Built up steel beams and columns
  • Composite floor slabs with 1.2mm deck slab & M30 grade concrete
  • Interior walls with double calcium silicate boards of 1.2mm thick
  • Structural steel fire proofed with cementacious fire proofing compound

THE SOLUTION

The actual solution, what Steelion proposed to The client to meet the objective.